PROJECT: ROYAL HOTEL ĐH Xây Dựng

206 222 0
PROJECT: ROYAL HOTEL  ĐH Xây Dựng

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

PROJECT: ROYAL HOTEL Mục lụcMục lục1PART I5ARCHITECTURE5( 10% )5INTRODUCTION77Figure 11 : Master Plan7ARCHITECTURAL AND TECHNICAL SOLUTION OF THE BUILDING82.1 Design of storeys plan8The functions of the storeys are divided reasonably and plainly8Storey 1 : insisting of parking area for car and motorbike , technical room, security room8Storey 2 : the main large lobby is the welcoming place of guests who use office and services, one large dinning room , one small dinning room …There are also functional rooms : toilets warehouses and security room .8Storey 3 : all area for working : large meeting room , small metting room and other working rooms.8Storey 4 – 10 : insisting of many bedrooms for guests, functional rooms : living room , toilets, balconys.8Roof storey : elevator technical room , water tank .89TECHNICAL AND INFRASTRUCTURE SOLTION18PART 2201. SELECTING STRUCTURAL SOLUTIONS212. TWODIMENSIONAL FRAME DESIGN DIAGRAM403. DETERMINING LOAD APPLYING ON FRAME421021.4Design document of building:1112.Selection1123.Material1124. Preliminary dimension of pile1124.Loading capacity of piles determination:1147.Determination of number and arrangement of piles1167.1Load distributing on each pile118Foundation beam system132PART III133CONSTRUCTION1331.4. Calculation of steel formwork1391.5 CALCULATION OF WORKLOAD AND LABOR1411.6. DESIGN CONSTRUCTION METHOD1441.6.1. Foundation construction1441.6.2Ground floor construction:1471.6.3. Massive volume concrete pouring method1482CONSTRUCTION MACHINES1492.1 Tower crane1492.2Static concrete pump1512.3Concrete truck1522.4Vibrator1525. SUPERSTRUCTURAL CONSTRUCTION1535.1PRELIMINARY METHOD FOR SUPERSTRUCTUREAL CONSTRUCTION1535.1.1 . Basic parameters1535.2Design formwork for column1555.3Design formwork for beam1575.4Corewall formwork1635.4.2.2Design formwork for slab1675.5GENERAL CONSTRUCTION METHOD1725.5.2Columns construction1735.5.2.1Surveying and positioning work1735.5.2.2Reinforcing work1735.5.2.3Installing column formwork1745.5.2.4Concrete work1745.5.2.5Uninstall formwork (removal)1755.5.3Beams and slab construction1755.5.3.1Installing formwork1755.5.3.2Reinforcing work1765.5.3.3Concrete work1775.5.3.4Curing concrete1795.5.3.5Uninstall formwork (removal)1795.5.3.6Defects rectification1805.5.3.7Staircase construction1815.5.4Calculation work volume1815.5.4.1Calculation of concrete volume1815.5.4.2Choose construction machines1905.5.54.3.2. Static concrete pump1925.5.64.3.3. Concrete truck1935.5.7Construction method of finishing task1965.5.7.1Brick up wall1965.5.7.2Plastering1975.5.7.3Gypsum wall1975.5.7.4Screed concrete layer1975.5.7.5Tiling1975.5.7.6Waterproof layer1975.5.7.7Electricity and water task197CONSTRUCTION SCHEDULE198CONSTRUCTION SITE LAYOUT201Define the quantity of materials needed for storage201Design temporary houses and temporary offices203Design water supply system204Power supply system206SAFETY IN CONSTRUCTION207Training, implement, examination of safety207Occupational safety in each stage of construction208Safety in working with equipment, machines on site210Environmental management210 PART I ARCHITECTURE ( 10% ) INSTRUCTOR : VU ANH TUANSTUDENT : NGUYEN HONG TRUONGCLASS : 57XE2STUDENT ID : 3833.57TASK :General introduction of the buildingArchitecture solution of the buildingDrawing plans layout and sectionsTechnical and infrastructure solutionINTRODUCTIONName of building : Royal Hotel .Investor : Royal International Stock Company .Address : Ba Dinh District , Ha Noi .Scale and feature of the building: The building is builded in an area of 4659.6m2 in which : + Area of the building: 1361 m2 + Height of the building: 39 m. Figure 11 : Master Plan Based on the feature of the plot of land, the requirement of the standards and regulations of the state, the design of master plan must be based on the use function of building’s type, technology lines to have clear functional zones and is also in accordance with the approved urban planning, to ensure scientific and aesthetic. The layout and architectural spaces have to ensure the requirements for fire protection, lighting, ventilation, noise, and isolation distance. For Royal Hotel , the front area is used for landscape and yard, so people can easily access to the building. Internal traffic is linked to external publictraffic of the city to have ventilation. In font of the building are main roads, huge yards that the fire truck can access and handle incidents. There is also a large sports ground in the background.ARCHITECTURAL AND TECHNICAL SOLUTION OF THE BUILDING2.1 Design of storeys plan The functions of the storeys are divided reasonably and plainly Storey 1 : insisting of parking area for car and motorbike , technical room, security room Storey 2 : the main large lobby is the welcoming place of guests who use office and services, one large dinning room , one small dinning room …There are also functional rooms : toilets warehouses and security room .Storey 3 : all area for working : large meeting room , small metting room and other working rooms.Storey 4 – 10 : insisting of many bedrooms for guests, functional rooms : living room , toilets, balconys.Roof storey : elevator technical room , water tank .Figure 12 : 1st floor planFigure 13: 2nd floor plan Figure 14: 3rd floor planFigure 15: Typical floor plan ( storey 4 – 10 ) Figure 16 : Roof plan  2.2 Design SectionSection shows the internal content of the building, dimension of basic components, and function of rooms. Based on the using feature and requirements of sanitation, ventilation for each area, the high of each level is selected as the following:Storey 1 : 3 mStorey 2 : 4.5 m Storey 3, 4  10 : 3.5 m Roof: 3.5 m Figure 17 : Section AA Figure 18 : Section BB 2.3 Design elevation Figure 19 : Elevation axis 112 Figure 110 : Elevation axis AF  TECHNICAL AND INFRASTRUCTURE SOLTION 3.1 Ventilation system Through the window system, natural ventilation is fully utilized. Besides, there is air conditioning system. The pipe system is laid in the vertical and horizontal technical box, distributes evenly to the places of consumption.3.2 Lighting systemNatural light is fully utilized. The window systems in all facades are glazed. In addition, artificial light is also arranged so that it can cover all points that need lighting. 3.3 Traffic system The vertical transportation system consists of two liftsFurthermore, there are also two escape staircases at two building’s sides. The horizontal transportation is arranged suitable for moving requirement. That is based on the function of each area. External trafic solution: Private path around the building.3.4 Power supplying system Electric system: 3 phase electric from local electric cabinet comes to electrical engineering room. After that, electric is distributed to all rooms. Moreover, there is a generator to supply electric automatically for elevator and hallway when electric system get incidents.Using power was delivered from power system of the city, building has transformer, beside there is a stand by generator in base floor. Lighting system ensures illumination from 20 – 40 lux. Special is middle corridor that is needed lighting all night and day for ensuring transportation. All offices have underground power line and electric tablet. Other rooms have more lighting requirement that was installed high quality lighting equipment. 3.5 Water supplying system and drainage system Water supplying system: Water is supplies by water supplying system of the city and contain in underground water tanks of the building. Water follow is controled by gauges. After that, water is pumped by pumps system and contained in roof water tanks. Water is supplied to restrooms of building by water pipe system from roof water tank automatically. Pipe system is hidden in floors, walls and technical boxes.Drainage system, Ventilation system: Drainage system consist of two parts. The first part is dirt drains and another part bring dung to septic tanks. Ventilation system has snorkel higher than elevation of roof by 700 mm.3.6 Fire fighting system Fire alarm system : Fire alarm detection devices are arranged in each room at every floor, public place of each floor. Fire alarm network is mounted alarm clocks and lamps. The management department controls fire as soon as receive the fire signal.Firefighting system: This system is designed based on the fire prevention requirements and other relevant standards (including fire preventing component, escape exits, firefighting water). CO2 cylinders are set at the intersections in all stories.3.7 Information technology system.Structured Cabling System for telephone and internetTV (cable, satellite)Public security system, CCTVAccess control system by magnetic card, fingerprint (Access Control)Public Address SystemAutomation System for Apartments (Home Automation)  PART 2STRUCTURE( 45% ) INSTRUCTOR : VU ANH TUAN STUDENT : NGUYEN HONG TRUONGCLASS : 57XE2STUDENT ID : 3833.57TASK :Selecting structural solutions Determine loads applying on the building CHAPTER I : SOLUTION IN STRUCTURE1. SELECTING STRUCTURAL SOLUTIONS1.1 Main structure Frame systemThis system is created from vertical bars (columns) connecting with horizontal bars (beams), called “node”. The plane frames are connected to each other in order to make a space frame. In order to increase the horizontal rigidity of frame, braces are added at some span along its height. This component works as a horizontal rigid wall.Advantages: Construction method is simple. This system has large space, flexible plan, and meets all using requirement of the building.Disadvantages: The horizontal rigidity of frame is small, so that horizontal load bearing capacity is low. The beams have big depth that affects to using function and increases the building’s height. Frame system is suitable for low rise building (less than 20 stories for reinforced concrete frame)Bearing wall system In this kind of structure, plane walls are the main bearing elements. In building where walls are installed in one direction, the stability of building in perpendicular direction is ensured by rigid walls. For high rise building, horizontal load is big so that the wall plates are designed to bear all horizontal and vertical loads. The horizontal load is transferred to wall plates through slab system that is absolutely considered as rigidity in its plane. Therefore, rigid walls work as continuous beams with high depth of section. Advantages: By using wall system we can remove the concentration of stress at beamcolumn connection. This system will have torsional rigidity if the walls are connected to each other. It also has great horizontal load bearing capacity, so that this system is suitable for building requiring partition space (house, hotel…).Disadvantages: Using space is limited by walls. The walls has high weight, high rigidity so that the effect of earthquake is big. The buildings will be wall system is commonly less than 20 stories.Framecore system Rigid walls are connected to each other to form a closed (or open) space frame, call “core”. Core has blank box in shape and receives loads then transfers them to earth. Most of the inner space is used for vertical transportation equipment (lift, staircase), technical pipe system (water pipe, electrical pipe). The main advantage of this system is its high bearing capacity of horizontal load and high torsional rigidity. The core works as a big continuous beam fixed to foundation1.2 Slab structure system For building, slab system has big effect on the working of structure. Select structure method is very important. Therefore, we must a proper analysis to choose the method which is suitable for building.Slabrib system Consist of beam system and slabAdvantages: Simple calculation. Used popular in Vietnam, because of structure technology plentiful.Disadvantages: The height of beam and the deflection of slab are very big. Therefore the height of building must be big. That is not saving for cost of materials. not saving space.Mass slab system with four ribs Consist of vertical beam system which divides slabs to smaller slabs with 4 ribs.Advantages: Decreasing the number of column inside the building. Therefore, that saves using space and makes the architecture of building more beautifully. The structure is suitable for the building which is required the high level of aesthetic and big using space .Disadvantages: Not saving, complicated construction. When the area of floor too large, we need to arrange more main beam. Thus, the disadvantage is big height of beam. Slab without beam:Advantages: The height of structure elements is small. Thus, that decreasing the height of building. Saving using space. Easy to divide space. Easy to arrange water and electric technology system. Suitable for building which has medium. Construction of the method is faster than beamslab method, because of not be taking time by reinforcing formwork, reinforcing steel of beam. Because, the height of beams decreases, vertical transportation decreases and cost of construction decreases. Horizontal load decreases, because of the height of building decreases.Disadvantages: The column is not connective. Thus stiffness of frame is smaller than “slab without beam” method. Therefore, horizontal load is loaded by rigid wall. The thickness of slab is big to ensuring the bending resistance ability and antipuncture ability. Thus, the weight of slab is big.1.3 ConclusionBecause, construction is high building which has the big distance between columns. Moreover, to ensure the aesthetic of building, I choose main structure method of building: Pile structure for foundation. Mass slab structure with four ribs. Main structure of building is framecore frame. They create a grid system which support for slab. Rigid walls and columns is buckling to foundation system.2. DETERMINATION OF PRELIMINARY DIMENSION OF ELEMENTS 2.1 Material Concrete grade B25: Rb= 14,5 MPa; Rbt = 1,05 Mpa; Eb =3.0x103 MPaSteel :+ Φ < 10 mm: Steel AI: Rs = Rsc = 225MPa.+ Φ ≥ 10 mm: Steel AII: Rs = Rsc = 280MPa.+ Steel AIII: Rs = Rsc = 365 MPa.2.2 Preliminary dimension of elements 2.2.1 Thickness of slab Thickness of slab in room Choose beam and slab floor solution is arranged through column and use secondary beam. Choosing the thickness of slab based on the formula :h_b>h_min=Dm L_1Legend: + D= 0.81.4: loading factor.+ m : Factor of edge supported slabs.m = 3545 : two way slab.m = 3035 : one way slab.+ L1: Shorter span of slab. With slab has the largest dimension (4.2m x 7.8m)D= 1.2 : loading factor.M= 45: Factor of edge supported slabs. ( two way slab)L1=3.9 : Shorter span of slab hs = 1.245 420 = 11.2 cm > hmin = 5 cm Choose the thickness of slab : hs = 12 cmThickness of slab in corridor hs = 1.245 270= 7.2 cm > hmin = 5 cm Choose the thickness of slab : hs = 8 cm 2.2.2 Preliminary dimension of beam The dimension of beam cross section based on experience formula:h_d=1m_d LLegend: m_d=812: with primary beamm_d=1216: with secondary beamL: Length of beam span.b_d=〖(0,30,5)h〗_da. Primary beam Length of span L1 = 7,8 m at CD span hd = 112 780 = 65 cm Choose the height of beam : hd = 65 cm Dimension of beam : bd x hd = 30x65 cm Length of span L2 = 2,7 m at DE span hd = 112 270 = 22,5 cm Choose the height of beam : hd = 30 cm Dimension of beam : bd x hd = 30x30 cm Dimension of conson beam L3 =1,2 m :bd x hd = 30x30 cm b. Secondary beamLength of span L4 = 4.8 m hd = 115 480 = 32 cm Choose the height of beam : hd = 40 cm Dimension of beam : bd x hd = 22x40 cmLength of span L5= 7.8 m hd= 115 780 = 52 cm Choose the height of beam : hd = 55 cm Dimension of beam : bd x hd = 22x55 cmOther secondary beams ( shorter span) Choose dimension of beam : 〖b_d xh〗_d= 22x40 cm2.2.3 . Dimension of column Deadload Type of slabMaterial layergtcgtcng1tt(mm)(daNm3)(daNm2)(daNm2)Floor 210 Ceramic Tile 400x400102000201.122Cement grout 75202000401.352RC Slab 12025003001.1330Ceiling plastering mortar 75152000301.339Total390443Type of slab Material layersgtcgtcng1tt(mm)(daNm3)(daNm2)(daNm2)Roof floor M12 terracotta tiles201200241.126.4Cement grout 75202000401.352Waterproof concrete layer402200881.3114.4Heat restrict tile10015001501.1165Slope mortar 302000601.378RC Slab 12025003001.1330Ceiling plastering mortar152000301.339Total 692805 Live loadNo.FunctionLoad (daNm2)Reliability coefficientTotalLongterm part1Bed room200701.22Living room, Dining room, Toilet200701.23Kitchen, Washing room3001001.24Hall, Lobby4001401.25Public toilet area200701.26Storage area5001m5001m1.27Restaurant3001001.28Roof areas are used150501.39Roof areas aren’t used75751.310Balcony, logia200701.211Garage5001801.212Office3001001.2Type of wall Material layersgtcgtcng1tt(mm)(daNm3)(daNm2)(daNm2)220 wallsolidTwo cement layer 302000601.378Brick 22018003961.1435,6Total 456513.6 Wall load 220 The demension of the column is preliminarily choosed by fomular :A=kR_b N Legend : A : crosssection area of column k : Affected factor by moment, k = 11,5. Rb : Compressed strength of concrete. N: Axial force caused by vertical loads N=S.q.n In which : + S : Bearing load area of a column in a storey + q : Preliminary load q= 12KNm2 = 1.2x102 Mpa + n : Number of storeysColunm at axis DD; EE excepting location at 6D;7D;6E;7E : Bearing load area S= ( 2.72 + 7.82 )x4.2=22.05 m2Assuming all the live loads on the floor are 300 daNm2. TTLoad Unit (daN)1Distributed load on floor and roof22,05.(443+300).9+(805+300)=1718142Selfweight of solid wall 220(3,9+4,2).3,5.513,6=14561Totally186375 daN Hence the crosssection of the column A = 1.3x18637514.5x105 = 0.167 m2Choose the dimension of the column : 30x60 cm (storey 13)30x55 cm (storey 46)30x50 cm (storey 7roof)Colunm at positions 6D;7D;6B;7B : Bearing load area S= (2,1+3,9)x(1,35+3,9)=31,5 m2 N=31,5x7792 + 10781,4 = 256229 daN A = 1.3x25622914.5x105 = 0,229 m2Choose the dimension of the column : 30x70 cm ( storey 13 ) 30x65 cm ( storey 66) 30x60 cm ( storey 7roof)Colunm at axis CC;FF excepting location at 6C;7C ;6F;7F: Bearing load area S= 3,9x4,2=16,38 m2 TTLoad Unit (daN)1Distributed load on floor and roof16,38.(443+300).9+(805+300)=1276332Selfweight of solid wall 220(3,9+4,2).3,5.513,6=14561Totally142194 daN The crosssection of the column A = 1.3x14219414.5x105 = 0.127 m2 Choose the dimension of the column : 30x45 cm (storey 13)30x40 cm (storey 46)30x35 cm (storey 7roof)

PROJECT: ROYAL HOTEL FINAL PROJECT Mục lục Mục lục .1 PART I ARCHITECTURE ( 10% ) INTRODUCTION FIGURE 1-1 : MASTER PLAN ARCHITECTURAL AND TECHNICAL SOLUTION OF THE BUILDING 2.1 DESIGN OF STOREYS PLAN THE FUNCTIONS OF THE STOREYS ARE DIVIDED REASONABLY AND PLAINLY .8 STOREY : INSISTING OF PARKING AREA FOR CAR AND MOTORBIKE , TECHNICAL ROOM, SECURITY ROOM STOREY : THE MAIN LARGE LOBBY IS THE WELCOMING PLACE OF GUESTS WHO USE OFFICE AND SERVICES, ONE LARGE DINNING ROOM , ONE SMALL DINNING ROOM …THERE ARE ALSO FUNCTIONAL ROOMS : TOILETS WAREHOUSES AND SECURITY ROOM STOREY : ALL AREA FOR WORKING : LARGE MEETING ROOM , SMALL METTING ROOM AND OTHER WORKING ROOMS STOREY – 10 : INSISTING OF MANY BEDROOMS FOR GUESTS, FUNCTIONAL ROOMS : LIVING ROOM , TOILETS, BALCONYS ROOF STOREY : ELEVATOR TECHNICAL ROOM , WATER TANK .8 TECHNICAL AND INFRASTRUCTURE SOLTION .18 PART 20 SELECTING STRUCTURAL SOLUTIONS 21 TWO-DIMENSIONAL FRAME DESIGN DIAGRAM .40 DETERMINING LOAD APPLYING ON FRAME .42 102 1.4 Design document of building: .111 2.Selection .112 3.Material .112 Preliminary dimension of pile 112 Loading capacity of piles determination: 114 Determination of number and arrangement of piles 116 7.1 Load distributing on each pile 118 Foundation beam system 132 PART III 133 CONSTRUCTION 133 1.4 Calculation of steel formwork .139 Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT 1.5 CALCULATION OF WORKLOAD AND LABOR 141 1.6 DESIGN CONSTRUCTION METHOD .144 1.6.1 Foundation construction 144 1.6.2 Ground floor construction: .147 1.6.3 Massive volume concrete pouring method 148 CONSTRUCTION MACHINES .149 2.1 Tower crane .149 2.2 Static concrete pump 151 2.3 Concrete truck .152 2.4 Vibrator 152 SUPERSTRUCTURAL CONSTRUCTION 153 5.1 5.5 PRELIMINARY METHOD FOR SUPERSTRUCTUREAL CONSTRUCTION 153 5.1.1 Basic parameters 153 5.2 Design formwork for column 155 5.3 Design formwork for beam 157 5.4 Core-wall formwork 163 5.4.2.2 Design formwork for slab 167 GENERAL CONSTRUCTION METHOD 172 5.5.2 COLUMNS CONSTRUCTION 173 5.5.2.1 Surveying and positioning work .173 5.5.2.2 Reinforcing work 173 5.5.2.3 Installing column formwork .174 5.5.2.4 Concrete work 174 5.5.2.5 Uninstall formwork (removal) 175 5.5.3 BEAMS AND SLAB CONSTRUCTION 175 5.5.3.1 Installing formwork 175 5.5.3.2 Reinforcing work 176 5.5.3.3 Concrete work 177 5.5.3.4 Curing concrete 179 5.5.3.5 Uninstall formwork (removal) 179 5.5.3.6 Defects rectification 180 5.5.3.7 Staircase construction 181 5.5.4 CALCULATION WORK VOLUME 181 5.5.4.1 Calculation of concrete volume .181 5.5.4.2 Choose construction machines 190 5.5.5 4.3.2 Static concrete pump .192 5.5.6 4.3.3 Concrete truck 193 5.5.7 CONSTRUCTION METHOD OF FINISHING TASK 196 5.5.7.1 Brick up wall .196 5.5.7.2 Plastering 197 5.5.7.3 Gypsum wall .197 5.5.7.4 Screed concrete layer .197 5.5.7.5 Tiling 197 5.5.7.6 Waterproof layer .197 5.5.7.7 Electricity and water task 197 CONSTRUCTION SCHEDULE 198 CONSTRUCTION SITE LAYOUT 201 DEFINE THE QUANTITY OF MATERIALS NEEDED FOR STORAGE 201 DESIGN TEMPORARY HOUSES AND TEMPORARY OFFICES 203 DESIGN WATER SUPPLY SYSTEM 204 POWER SUPPLY SYSTEM 206 Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT SAFETY IN CONSTRUCTION .207 TRAINING, IMPLEMENT, EXAMINATION OF SAFETY 207 OCCUPATIONAL SAFETY IN EACH STAGE OF CONSTRUCTION .208 SAFETY IN WORKING WITH EQUIPMENT, MACHINES ON SITE 210 ENVIRONMENTAL MANAGEMENT 210 PART I ARCHITECTURE ( 10% ) INSTRUCTOR : VU ANH TUAN STUDENT : NGUYEN HONG TRUONG CLASS : 57XE2 STUDENT ID : 3833.57 Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT TASK : - General introduction of the building - Architecture solution of the building - Drawing plans layout and sections - Technical and infrastructure solution Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT INTRODUCTION - Name of building : Royal Hotel Investor : Royal International Stock Company Address : Ba Dinh District , Ha Noi Scale and feature of the building: The building is builded in an area of 4659.6m2 in which : + Area of the building: 1361 m2 + Height of the building: 39 m Figure 1-1 : Master Plan - Based on the feature of the plot of land, the requirement of the standards and regulations of the state, the design of master plan must be based on the use function of building’s type, technology lines to have clear functional zones and is also in accordance with the approved urban planning, to ensure scientific and aesthetic The layout and architectural spaces have to ensure the requirements for fire protection, lighting, ventilation, noise, and isolation distance For Royal Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT Hotel , the front area is used for landscape and yard, so people can easily access to the building Internal traffic is linked to external public-traffic of the city to have ventilation In font of the building are main roads, huge yards that the fire truck can access and handle incidents There is also a large sports ground in the background ARCHITECTURAL AND TECHNICAL SOLUTION OF THE BUILDING 2.1 Design of storeys plan The functions of the storeys are divided reasonably and plainly - Storey : insisting of parking area for car and motorbike , technical room, security room - Storey : the main large lobby is the welcoming place of guests who use office and services, one large dinning room , one small dinning room …There are also functional rooms : toilets warehouses and security room - Storey : all area for working : large meeting room , small metting room and other working rooms - Storey – 10 : insisting of many bedrooms for guests, functional rooms : living room , toilets, balconys - Roof storey : elevator technical room , water tank Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT a a FLOOR plan 1- l evel +0.00 (SCALE 1/150) a b b 10 11 12 b b d d c e e c f f a - Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT Figure 1-2 : 1st floor plan Student: NGUYEN HONG TRUONG – Class: 57XE2 Page PROJECT: ROYAL HOTEL FINAL PROJECT Figure 1-3: 2nd floor plan Student: NGUYEN HONG TRUONG – Class: 57XE2 Page FINAL PROJECT 10 11 12 b b d d c e e c f a b b 10 11 12 f a PROJECT: ROYAL HOTEL Figure 1-4: 3rd floor plan Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 10 PROJECT: ROYAL HOTEL FINAL PROJECT Volumn of concrete mortar B5 V  Sslab �   �   m ) Wall plastering area of each floor Inner: S  0.8 �  �12))   m ) => Manday: 115.68 �0.15= 17 Outer: S  0.8 � �2   m ) => manday: 110.88 �0.22= 25 ( 0.15;0.2 norm 1776) 5.5.7.3Gypsum wall From 1st to the 9th floor Area of gypsum wall of each floor S  L �h  103 �3.5  360.05(m ) 5.5.7.4Screed concrete layer Volumn of concrete mortar B5 Ground and floor 1-9: V  Sslab �   �   m ) Roof: V  Sslab �  1055.7 �0.025  26.4(m ) 5.5.7.5Tiling Tiling area of slab: S �Sslab  993.3(m ) 5.5.7.6Waterproof layer Using Shell Flintkote bitumen emulsion for the basement, roof, to the walls and to wet areas to create a seamless barrier to keep water out Area of waterproofing layer Ground: A  1004.7(m ) Floor 1-9: A  933.3(m ) Roof: A  1055.7(m ) 5.5.7.7Electricity and water task Preliminary choose that 0,2hour/m2 Time to finish: T  0.2 �  186.6(hour / floor)  23.3(shift / floor) Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 192 PROJECT: ROYAL HOTEL FINAL PROJECT CONSTRUCTION SCHEDULE Major principles organization: as below are required for successful construction Optimal Economic effectiveness: the selected construction solutions must meet the following requirements: - Such solutions are able to shorten the construction time - To intensify labor productivity and save labor cost - To save construction cost - To improve the construction quality - To meet some general and safety, environment sanitation, etc particular requirements like: labor health & Use of mechanization methods, advanced technical equipment and tools: This approach is following the development trend of construction technologies wherein more and more machines are applied in construction to save manpower The production organization method can be changed from Production on site to production in industrial plants (where details needed for the construction on site are prepared and produced Construction sites are places where details are fabricated to make final products) Optimal Organization of work: This approach requires construction period to be divided into separate manipulations, aiming to appropriate allocation of manpower, intensive professionalization for enhancing working productivity and workers skill Working methods are required to be changed, in which excessive or unnecessary manipulations would be eliminated (optimal working) Effective time spending, restricting idle time, etc Standardization and modularization for construction: Standardization is the establishment of technical standards and codes for better application in actual condition This would help construction to be economically and technically effective Standardization sets out particular orders and technical requirements which are obligatory for the construction period Modularization is the establishment of regulars and specifications for products like dimension, nature… in the way that such regulars and specifications would be commonly applied and could be convertible or replaceable in the structure of the project CONSTRUCTION OGANIZATION METHOD Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 193 PROJECT: ROYAL HOTEL FINAL PROJECT Currently, there are 03 major methods for construction organization, respectively: - Sequence method - Simultaneous method - “Line of balance” method Each method has its own advantages and disadvantages, would be partially or fully applied depended on particular conditions, with a purpose of the most effectiveness of production and construction For the super structure of this building, the “Line of balance” method is the most suitable method This is the logical combination of Sequence method and Simultaneous method, which narrows the disadvantages and enhance the advantages of both above methods With this method, the construction period of one product is divided into smaller phases, construction time for each phase is all similar The coordination is smoothly deployed in term of time and space based on the following principles: - Smaller phases of same products would be implemented by sequence, from one product to another product - Smaller phases of different products would be implemented simultaneously on different products In general, the construction method based on “line of balance” on is the most advanced method thanks to appropriate allocation of manpower, specialization of manipulations and cooperation in production Its outstanding features are high level of specialization of particular locations and positions on construction site; narrowing the list of products for manufacturing; balancing the production capacity; and the continuous, smooth and simultaneous performance of smaller phases This method at last results in shorter time of production, more products, lower cost and lower price, constant requirements of manpower and materials This method in construction has 02 main features: - As the construction product is associated with land and is big in size, it is required to also move the workers with their accompanied tools/equipment from one to the other locations and spaces This makes the “Line of balance” method different with the “industrial line” where the workers and their tools stand still while products keep on moving Consequently, the organization of “production line” method in construction is much harder - As the construction product is unique and diversified, most of production line is for short-term use Its stability is little or very limited This requires re-organization for construction of new project after a short period of time Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 194 PROJECT: ROYAL HOTEL FINAL PROJECT Table III.12 Duration of typical slab task Task Name Duration the 3td floor 17 days Resource Names Installation column reinforcement day NC[22] Installation column formwork day NC[27] Pouring concrete column day NC[10] Dismantlement column formwork day NC[12] Installation beam and slab formwork 2days NC[95] Installation beam and slab reinforcement days NC[107] Pouring beam and slab concrete day NC[42] Curing concrete days NC[2] Dismantlement beam and slab formwork day NC[82] CONSTRUCTION SITE LAYOUT Define the quantity of materials needed for storage Qdt  q max Tdt Legend: qmax: maximum material quantity consumed in a day Qmax= Q.k (Q total quantities consumed in a day, k=1,2-1,6 is factor of irregular use) Tdt: preservation time for regular materials, includes: Means of delivery Materials type Truck (day) Sand, gravel stones, Cement, steel bricks, Wood 15 km 2-3 3-5 4-6 6-10 5-10 10-15 Choose: Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 195 PROJECT: ROYAL HOTEL FINAL PROJECT Tdt=4 days for cement, bricks, steel Tdt=5 days formwork Tdt=2 days for sand, stones, gravel Reinforcement task: 8.9 (T/day) Brick-up wall task: Wall 220: 73.81m3 Norm 1776: 1m3 wall 220 have 550 blocks, 0.29 m3 mortar Hence: the total Brick : 40595 blocks � � Mortar: 21.4 m � Using mortar class M75 has: 0.3 T cement and 1.12m3 sand in m3 mortar Cement : 6.72 T � � Black sand: 23.97 m � Plastering task: consider the thickness of every plastering layer 1.5cm V  S.  993.3.0,015  14.9 (m ) Cement : 4.47 T � � Black sand: 16.69 m � Hence, we have the quantity of material in storage is: 3 Black sand: (23.97m  16.69m ) �2  81.3 (m ) Cement: (6.72T  4.47T) �5  55.95T Reinforcement: 8.9T �5  44.5T  �  67658 Blocks Brick: Steel formwork volume: V  (1476.2) �0.05  73.81(m ) Storage areas Fc is the area directly contain materials, calculated by: Fc  D max d In which: Dmax: Maximum amount of materials contain on warehouse d: the standard material quantity defined by norm contained on 1m of the storage spaces Storage area include access road is calculated: Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 196 PROJECT: ROYAL HOTEL FINAL PROJECT S   �Fc In which: α- site using factor =1.5-1.7 for general storehouses =1.4-1.6 for closed storage =1.2-1.3 for out-door storage spaces =1.1-1.2 for large out-door storage spaces where for big containers No Material Unit Volume Storage Sand m3 81.3 a S 23.22 1.2 27.86 Reinforcement T 22 Haft out-door 5.5 1.5 8.8 Formwork m3 73.81 Haft out-door 1.5 49.2 1.5 73.8 Brick Block 67658 Out-door 700 96.65 1.2 64.27 Cement T 55.95 Close 1.3 43.04 1.5 64.5 Out-door Norm Fc 3.5 Design temporary houses and temporary offices Calculation of site manpower Group of main workers (N1): N1  36 (Workers) Group of supporting workers (N2): N  0.2N1  0.2 �  (Workers) Group of technical staffs (N3): N  0.05(N1  N )  0.05 �(8  36)  (People) Group of administration and commercial staffs (N4): N  005(N1  N )  0.05 �(8  36)  (people) Group of supporting staffs (N5): N  0.03(N1  N )  0.03 �  )  (people) Staffs for coordination of general activities: N  0,08(N1  N  N  N  N )  0.08 �  (people) From daily schedule on the site in a year have 2% workers sick and 4% not go to site Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 197 PROJECT: ROYAL HOTEL => Total site manpower FINAL PROJECT N  �1.06N i 1.06 �  56 (people) Calculation of temporary house area Temporary house for workers (4m2/worker): F1  (N1  N ) �f1  44 �4  176 (m2) Temporary office for technical engineer and administration and economical staffs (4m 2/worker): F2  (N  N ) �f  �4  24 (m2) Temporary house for shower (25 people/2,5m2.room): The number of shower room: G 56  3 25 25 (Rooms) F3  R.f  �2,5  7.5 (m2) R Canteen 40m2/100 people: F4  G 56 �40  �40  22.4 100 100 (m2) Toilets (25 people/2,5m2): F5  G 56 �2.5  �2.5  5.6 25 25 (m2) Clinics 0,04m2/person F6  G �0.04  56 �0.04  2.24 (m2) Security room F7  10 (m ) Head-office F8  16 (m ) Clinics is required high quality use fixed monolithic structure Staff house, management house, public house use pre-fabricated structures Toilet use movable type Design water supply system Water serve construction Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 198 PROJECT: ROYAL HOTEL FINAL PROJECT n Q  1, �A i i 1 8.3600 k g Legend: n=3- Number of water using resource Ai- Quantity of water server for construction equipment kg=2,5- Factor of irregular using water 1,2- Factor of arising water on site A1  (14.9  73.81) / 5.250  4435.5 (l/shift) - Water for mortar mixer area A  60.200  12000 (l/shift) - Water for curing concrete A  22495.0,  4499 (l/shift) - Water for washing brick 4435.5  12000  4499 Q1  1.2 �2.5 � �3600  2.18 (l/s) Domestic water This kind of water using for living activities on site N Q B.k max g 8.3600 Which: N max  56 - Maximum people on site B  18 (l) - Amount of water for a person in a day follow standard kg  Q2  - Factor of irregular using water 56 �18 �2  0.07 (l/s) �3600 Water supply for housing unit Including water for washing, having shower, cooking…are calculated by formula: Not locate temporary house for workers on site Water for firefighting Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 199 PROJECT: ROYAL HOTEL FINAL PROJECT Water is also needed for firefighting in the building and housing units, it depends on the number of occupations and the area of the building and units, can be determined about 10-20 litter per second or checked in standard tables Choose Q  10 (l/s) Because Q1  Q2  Q Q  0.7 �(Q1  Q2 )  Q4  0.7 �(2.18  0.7)  10  12.88(l / s) Calculate dimension (diameter) of pumping Main pipe: D 4Q �12.88   0.12m  120mm .v.1000 3.14 �1.2 �1000 Choose water supply pipe diameter D=150mm Water supplies: From water system of city for domestic The pile system is placed 25cm depth in ground Power supply system Calculation of consumed power on site PK PK Pt  1,1(� 1  � 2  �P3K  �P4 K ) cos  cos  Legend: �P is rated power of machine using engine Mortar mixer: P  3, 24kW Vibrator: P  1�10  10kW Tower crane: P  21, 2kW Hoist: P  7,5 �2  15kW �P  49.44kW Cosφ=0.68 is power factor K1=0.75-unequal using factor of electrical loads �P  40kW - required power of manufacturing process (welding machine) Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 200 PROJECT: ROYAL HOTEL FINAL PROJECT Cosφ=0.65; K2=0.7 �P  (10 �15%) �P1  10kW - required power of outdoor and indoor lighting K3=0.9 �P  20kW is power using another furniture K4=0.9 Pt  137.07kW Qt  Pt 137.07   185.23kW cos tb 0.74 S  Pt  Q t  137.07  185.232  230kW Design power network Use the national electrical network Select phase power, with aluminum wire Choose cross-section of wire: A PL 137.07 �0.07   3.83mm C.U% 50 �0,05 Choose S=4mm2 for all the electrical wire Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 201 PROJECT: ROYAL HOTEL FINAL PROJECT SAFETY IN CONSTRUCTION Training, implement, examination of safety Officers and officials working in the area of construction are covered by the basic training on occupational safety and check on their level, the sense of preserving the occupational safety for themselves and for the surrounding Machines, vehicles, construction equipment put into operation must be checked the safety of device (register certificate) The staffs are checked on their skill and health, to assign task to suit every type of work Who has not passed the training will not operate the equipment requiring professional level To limit the scope of activity and areas of the worker, must have signages All those who not have the task in the region are limited to ensure safety (transformer, breaker electric, etc) Storages, auxiliary shops must be arranged reasonably, pay attention to fire resistance and safety After formwork dismantlement, shores, boards, scaffold must be cleared and arranged into categories For scaffolding when its installation is completed, the technicians must inspect before use People with heart disease, high blood pressure not being assigned work on high level Workers working on scaffolding must wear safety belts, hard hats Don't be running jokes Do not sit on the railing, not climbing the outside the rail When there is rain or wind which is more than level 6, thick fog, not working on scaffolding Scaffolding must be checked before using again Dismantling scaffolding must be instructed by the technical staff Before dismantlement, must clean up tool and materials on the working platform The boards, scaffolds when dismantling are not allowed to throw down from high level Occupational safety in each stage of construction In concrete tasks All workers must be trained occupational safety and equipped labor protection The exit under region being poured concrete is banned with signage When constructing at depth greater than 1.5m, the hose for pumping concrete must be fixed to formwork components or working platform When using vibrator, connect vibrator to earth by insulated wire and use the insulated wire connecting from power distribution board to vibrator’s engine Clean vibrator and wrap its wire when not use Workers operating must be equipped insulated boot and other personal protection tools Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 202 PROJECT: ROYAL HOTEL FINAL PROJECT When curing concrete, must use scaffold, not stand on shores or formwork’s edges In reinforcement tasks Fabricating rebar is done in private sector, having barricades and signage Table for rebar fabrication must be fixed surely, fabricated rebar must put on right place When straightening steel roll by machine, have measures for covering cylinder and avoid rebar to slip to come out before operating Cable top of winch is connected to rebar which needs straightening by special equipment, only dismantle the connection when the winch off Forbid to use the engine for cutting steel segments shorter than 80 cm without the safety devices When the installation of reinforcement near power lines, must cut power off, if not, must take measures to prevent the reinforcement touching power line In Formwork and scaffold tasks During construction, using formworks or scaffolds must follow the design approved by authority Prohibit not to use scaffolding when: does not meet the technical requirements and safety conditions as inadequate anchor hook, ligaments or they are anchored to the parts having poor structural stability Do not use the scaffold or formwork when they are deformed, cracked, and shores when they are placed on which are unstable or likely to slip or structural components not being calculated bearing capacity yet When the erection of scaffolding systems, need to the following: anchor the scaffolds firmly to the building and the location of the anchor hook should be set according to the design When the anchor hook position coincides with the hole in the wall, have to make bracing inside to anchor Dismantling formwork must proceed in sequence and according to the instructions in the design The dismantling area must be fenced to prevent people or vehicles go through Formwork in use is large board combined from smaller plates, ensure they are firm and avoid impact to other structures when installation Must have working platform when installing formwork whose height not exceed 6m and when the installation of formwork height greater than m, delivered to experienced workers Ban placing or arranging the formwork boards or other components of formwork slip surface On the working platform and keep the load allowed and only placed the material on the platform in the position specified, must clean up excess material, waste material on the platform and gathered to the place specified Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 203 PROJECT: ROYAL HOTEL FINAL PROJECT Only dismantling formwork after concrete meets its enough strength, under guidance of technical staffs Dismantling formwork must follow the logical sequence, have measures to prevent formwork falling and fences, signage around the dismantlement area When dismantlement of formwork, always observe the status of structure, if there are any phenomenon of deformation, inform the technical staffs to have treatment measure timely In use of power in construction Electrical workers must be learned, tested and certified satisfactory electrical safety Electrical worker who in a construction area have to master power supply diagram of that area The site must have its electrical network diagrams, have general circuit breaker, breaker segments to be able to cut whole or each sector on site when needed The wires using on site must be insulated wires, are on the column at height of at least 2.5m toward construction plan and 5m toward where the vehicles pass The wires under 2.5 m from the construction plan must be rubbercoated wires All electrical equipment must be protected short circuit and overload protection devices (fuses, relays, aptomat, etc.) must be selected in accordance with the voltage and current of the device or group of devices that are protected When using the electric handheld devices, workers are not on ladder and stand on safety platform For heavy tools, workers have to make hanger or other ways ensuring safety Workers must take gloves, boots and shoes Only the power workers, who are directly assigned to newly repair, match or disconnect electrical appliances off the grid Only open the cover of equipment, any repairs when the power system is off Ban use of fixed lights to be handheld lights The lights at work are set at the positions such reasonably that not cause any troubles to the workers In fire resistance Comply the rules of fire resistance and take them to the construction site for people to study Place the firefighting equipment as sandbags, water tanks at the location having combustible materials Layout locations to take the water for fire resistance (well and mobile water tank), ready when the fire occurs Arrange workers who have been trained on fire rescue ready when a fire occurs Storages of materials, offices are equipped with fire protection systems Safety in working with equipment, machines on site Vibrator Only workers who are assigned operate vibrators When operating, pay attention to the following: Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 204 PROJECT: ROYAL HOTEL FINAL PROJECT Check the power line from the power net to the vibrator Only switch the vibrator on after putting the breaker on, see the vibrator shake then bring it to work Not allow greater ¾ length of the needle vibrator to be deep in concrete When engine stop working, take the needle vibrator out of concrete Do not leave heavy thing on the flexible hose, the radius of curvature of the hose is not less than 40 cm and must not bend into segments The workers operating vibrator only dismantle its needle by specified equipment Not let the water be into the needle and hose When the needle gets jammed or the engine does not turn, must cut the needle form engine right now and inform to technical staff to have treatment Environmental management Master plan sanitation Layout the location to wash motorbike and construction vehicles before they go out of the site Spray water on the roads around the site to prevent dust Arrange trucks to transport waste materials out of the site at time allowed of city traffic Arrange dedicated group to industrial hygiene and sanitation activities in and around the site Waste Wastewater, surface water is collected to makeshift trench connecting to the network of the region, not to the spill Waste at the site must be poured at the regulation location, every week, they are bring out of the site Arrange a private toilet area for the workers in the site and group of people regularly clean to avoid causing pollution to the surroundings Do not burn waste in construction site Noisy and dust resistance Due to site locates near residential areas, so pay attention to environmental problems, noise and dust resistance Time of gathering supplies and vehicles will be deployed appropriately Vehicles transporting materials to the site must have canvas covering, avoid sand, rock falling on the road The velocity of vehicles running on site is in limitation of km/h to avoid stirring dust In dry and sunny days, the contractor will spray water against a construction dust and wash for roads around construction sites and residential areas The construction equipment brought to the site must be tested and are the new devices restricting noise Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 205 PROJECT: ROYAL HOTEL FINAL PROJECT The car carrying the materials will be covered with canvas Once out of the site, all vehicles must be cleaned The waste is collected and dumped the right places Vehicles carrying materials must have the canvas cover to resist dust, rock falling on the road Restrict the noise level to the maximum level Control of leaking oil, chemicals Wastewater, grease, chemicals in the process of construction are treated or led to location regulated, not to spill, cause environmental pollution and bad impacts to the site (absolutely not to grease blended into the material storage yards, sand, stones etc.) Figure II.15 Foundation under column C1, C4 113 Figure II.16 Foundation under two column C2+ C3 113 Figure II.17 Pile bending moment diagram when transporting 115 Figure II.18 Pile bending moment diagram when hanging 115 Figure II.19 Tensile force on the hook 116 Figure II.20 Punching diagram of pile cap .119 Figure III.8 Column formwork detailing .152 Figure III.9 Beam formwork detailing 154 Total load for checking durability condition: 154 Figure III.10 Bottom formwork calculation diagram .155 Figure III.11 Upper girder calculation diagram .155 Figure III.12 Under girger calculation diagram .156 Figure III.13 Side formwork calculation diagram 158 Figure III.14 Formwork plan layout of a slab area 164 Loads apply on slab formwork .164 Figure III.15 Slab formwork calculation diagram 165 Figure III.16 Upper girder calculation diagram .166 Figure III.17 Under girder calculation diagram .167 Figure III.19 Locate crane on site 190 Student: NGUYEN HONG TRUONG – Class: 57XE2 Page 206

Ngày đăng: 25/03/2018, 13:18

Từ khóa liên quan

Mục lục

  • Mục lục

  • PART I

  • ARCHITECTURE

  • ( 10% )

  • INTRODUCTION

    • Figure 1-1 : Master Plan

    • ARCHITECTURAL AND TECHNICAL SOLUTION OF THE BUILDING

      • 2.1 Design of storeys plan

      • The functions of the storeys are divided reasonably and plainly

      • Storey 1 : insisting of parking area for car and motorbike , technical room, security room

      • Storey 2 : the main large lobby is the welcoming place of guests who use office and services, one large dinning room , one small dinning room …There are also functional rooms : toilets warehouses and security room .

      • Storey 3 : all area for working : large meeting room , small metting room and other working rooms.

      • Storey 4 – 10 : insisting of many bedrooms for guests, functional rooms : living room , toilets, balconys.

      • Roof storey : elevator technical room , water tank .

      • TECHNICAL AND INFRASTRUCTURE SOLTION

      • PART 2

      • 1. SELECTING STRUCTURAL SOLUTIONS

      • 2. TWO-DIMENSIONAL FRAME DESIGN DIAGRAM

      • 3. DETERMINING LOAD APPLYING ON FRAME

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan