project management book phần 4 pdf

40 332 0
project management book phần 4 pdf

Đang tải... (xem toàn văn)

Tài liệu hạn chế xem trước, để xem đầy đủ mời bạn chọn Tải xuống

Thông tin tài liệu

5.1 Scope Planning Defining and managing the project scope influences the project’s overall success. Each project requires a careful balance of tools, data sources, methodologies, processes and procedures, and other factors to ensure that the effort expended on scoping activities is commensurate with the project’s size, complexity, and importance. For example, a critical project could merit formal, thorough, and time- intensive scoping activities, while a routine project could require substantially less documentation and scrutiny. The project management team documents these scope management decisions in the project scope management plan. The project scope management plan is a planning tool describing how the team will define the project scope, develop the detailed project scope statement, define and develop the work breakdown structure, verify the project scope, and control the project scope. The development of the project scope management plan and the detailing of the project scope begin with the analysis of information contained in the project charter (Section 4.1), the preliminary project scope statement (Section 4.2), the latest approved version of the project management plan (Section 4.3), historical information contained in the organizational process assets (Section 4.1.1.4), and any relevant enterprise environmental factors (Section 4.1.1.3). 5 Figure 5-3. Scope Planning: Inputs, Tools & Techniques, and Outputs 5.1.1 Scope Planning: Inputs .1 Enterprise Environmental Factors Enterprise environmental factors include items such as the organization’s culture, infrastructure, tools, human resources, personnel policies, and marketplace conditions that could affect how project scope is managed. .2 Organizational Process Assets Organizational process assets are the formal and informal policies, procedures, and guidelines that could impact how the project’s scope is managed. Those of particular interest to project scope planning include: A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 107 NAVIGATION LINKS ABBREVIATION LIST Chapter 5 − Project Scope Management • Organizational policies as they pertain to project scope planning and management • Organizational procedures related to project scope planning and management • Historical information about previous projects that may be located in the lessons learned knowledge base. .3 Project Charter Described in Section 4.1. .4 Preliminary Project Scope Statement Described in Section 4.2. .5 Project Management Plan Described in the introduction to Section 4.3. 5.1.2 Scope Planning: Tools and Techniques .1 Expert Judgment Expert judgment related to how equivalent projects have managed scope is used in developing the project scope management plan. .2 Templates, Forms, Standards Templates could include work breakdown structure templates, scope management plan templates, and project scope change control forms. 5.1.3 Scope Planning: Outputs .1 Project Scope Management Plan The project scope management plan provides guidance on how project scope will be defined, documented, verified, managed, and controlled by the project management team. The components of a project scope management plan include: • A process to prepare a detailed project scope statement based upon the preliminary project scope statement • A process that enables the creation of the WBS from the detailed project scope statement, and establishes how the WBS will be maintained and approved • A process that specifies how formal verification and acceptance of the completed project deliverables will be obtained • A process to control how requests for changes to the detailed project scope statement will be processed. This process is directly linked to the integrated change control process (Section 4.6). A project scope management plan is contained in, or is a subsidiary of, the project management plan. The project scope management plan can be informal and broadly framed, or formal and highly detailed, based on the needs of the project. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 108 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS ABBREVIATION LIST 5.2 Scope Definition The preparation of a detailed project scope statement is critical to project success and builds upon the major deliverables, assumptions, and constraints that are documented during project initiation in the preliminary project scope statement. During planning, the project scope is defined and described with greater specificity because more information about the project is known. Stakeholder needs, wants, and expectations are analyzed and converted into requirements. The assumptions and constraints are analyzed for completeness, with additional assumptions and constraints added as necessary. The project team and other stakeholders, who have additional insight into the preliminary project scope statement, can perform and prepare the analyses. 5 Figure 5-4. Scope Definition: Inputs, Tools & Techniques, and Outputs 5.2.1 Scope Definition: Inputs .1 Organizational Process Assets Described in Section 4.1.1.4. .2 Project Charter If a project charter is not used in a performing organization, then comparable information needs to be acquired or developed, and used to develop the detailed project scope statement. .3 Preliminary Project Scope Statement If a preliminary project scope statement is not used in a performing organization, then comparable information, including the product scope description, needs to be acquired or developed and used to develop the detailed project scope statement. .4 Project Scope Management Plan Described in Section 5.1.3.1. .5 Approved Change Requests Approved change requests (Section 4.4) can cause a change to project scope, project quality, estimated costs, or project schedule. Changes are often identified and approved while the work of the project is ongoing. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 109 NAVIGATION LINKS ABBREVIATION LIST Chapter 5 − Project Scope Management 5.2.2 Scope Definition: Tools and Techniques .1 Product Analysis Each application area has one or more generally accepted methods for translating project objectives into tangible deliverables and requirements. Product analysis includes techniques such as product breakdown, systems analysis, systems engineering, value engineering, value analysis, and functional analysis. .2 Alternatives Identification Identifying alternatives is a technique used to generate different approaches to execute and perform the work of the project. A variety of general management techniques is often used here, the most common of which are brainstorming and lateral thinking. .3 Expert Judgment Each application area has experts who can be used to develop portions of the detailed project scope statement. .4 Stakeholder Analysis Stakeholder analysis identifies the influence and interests of the various stakeholders and documents their needs, wants, and expectations. The analysis then selects, prioritizes, and quantifies the needs, wants, and expectations to create requirements. Unquantifiable expectations, such as customer satisfaction, are subjective and entail a high risk of being successfully accomplished. Stakeholders’ interests may be positively or negatively affected by execution or completion of the project and they may also exert influence over the project and its deliverables. 5.2.3 Scope Definition: Outputs .1 Project Scope Statement The project scope statement describes, in detail, the project’s deliverables and the work required to create those deliverables. The project scope statement also provides a common understanding of the project scope among all project stakeholders and describes the project’s major objectives. It also enables the project team to perform more detailed planning, guides the project team’s work during execution, and provides the baseline for evaluating whether requests for changes or additional work are contained within or outside the project’s boundaries. The degree and level of detail to which the project scope statement defines what work will be performed and what work is excluded can determine how well the project management team can control the overall project scope. Managing the project scope, in turn, can determine how well the project management team can plan, manage, and control the execution of the project. The detailed project scope statement includes, either directly or by reference to other documents: A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 110 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS ABBREVIATION LIST • Project objectives. Project objectives include the measurable success criteria of the project. Projects may have a wide variety of business, cost, schedule, technical, and quality objectives. Project objectives can also include cost, schedule, and quality targets. Each project objective has attributes such as cost, a metric such as United States dollars, and an absolute or relative value such as less than 1.5 million dollars. • Product scope description. Describes the characteristics of the product, service, or result that the project was undertaken to create. These characteristics will generally have less detail in early phases and more detail in later phases as the product characteristics are progressively elaborated. While the form and substance of the characteristics will vary, the scope description should always provide sufficient detail to support later project scope planning. 5 • Project requirements. Describes the conditions or capabilities that must be met or possessed by the deliverables of the project to satisfy a contract, standard, specification, or other formally imposed documents. Stakeholder analyses of all stakeholder needs, wants, and expectations are translated into prioritized requirements. • Project boundaries. Identifies generally what is included within the project. It states explicitly what is excluded from the project, if a stakeholder might assume that a particular product, service, or result could be a component of the project. • Project deliverables. Deliverables (Section 4.4.3.1) include both the outputs that comprise the product or service of the project, as well as ancillary results, such as project management reports and documentation. Depending on the project scope statement, the deliverables may be described at a summary level or in great detail. • Product acceptance criteria. Defines the process and criteria for accepting completed products. • Project constraints. Lists and describes the specific project constraints associated with the project scope that limit the team’s options. For example, a predefined budget or any imposed dates (schedule milestones) that are issued by the customer or performing organization are included. When a project is performed under contract, contractual provisions will generally be constraints. The constraints listed in the detailed project scope statement are typically more numerous and more detailed than the constraints listed in the project charter. • Project assumptions. Lists and describes the specific project assumptions associated with the project scope and the potential impact of those assumptions if they prove to be false. Project teams frequently identify, document, and validate assumptions as part of their planning process. The assumptions listed in the detailed project scope statement are typically more numerous and more detailed than the assumptions listed in the project charter. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 111 NAVIGATION LINKS ABBREVIATION LIST Chapter 5 − Project Scope Management • Initial project organization. The members of the project team, as well as stakeholders, are identified. The organization of the project is also documented. • Initial defined risks. Identifies the known risks. • Schedule milestones. The customer or performing organization can identify milestones and can place imposed dates on those schedule milestones. These dates can be addressed as schedule constraints. • Fund limitation. Describes any limitation placed upon funding for the project, whether in total value or over specified time frames. • Cost estimate. The project’s cost estimate factors into the project’s expected overall cost, and is usually preceded by a modifier that provides some indication of accuracy, such as conceptual or definitive. • Project configuration management requirements. Describes the level of configuration management and change control to be implemented on the project. • Project specifications. Identifies those specification documents with which the project should comply. • Approval requirements. Identifies approval requirements that can be applied to items such as project objectives, deliverables, documents, and work. .2 Requested Changes Requested changes to the project management plan and its subsidiary plans may be developed during the Scope Definition process. Requested changes are processed for review and disposition through the Integrated Change Control process. .3 Project Scope Management Plan (Updates) The project scope management plan component of the project management plan may need to be updated to include approved change requests resulting from the project’s Scope Definition process. 5.3 Create WBS The WBS is a deliverable-oriented hierarchical decomposition of the work to be executed by the project team, to accomplish the project objectives and create the required deliverables. The WBS organizes and defines the total scope of the project. The WBS subdivides the project work into smaller, more manageable pieces of work, with each descending level of the WBS representing an increasingly detailed definition of the project work. The planned work contained within the lowest-level WBS components, which are called work packages, can be scheduled, cost estimated, monitored, and controlled. The WBS represents the work specified in the current approved project scope statement. Components comprising the WBS assist the stakeholders in viewing the deliverables (Section 4.4.3.1) of the project. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 112 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS ABBREVIATION LIST 5 Figure 5-5. Create WBS: Inputs, Tools & Techniques, and Outputs 5.3.1 Create WBS: Inputs .1 Organizational Process Assets Described in Section 4.1.1.4. .2 Project Scope Statement Described in Section 5.2.3.1. .3 Project Scope Management Plan Described in Section 5.2.1.4. .4 Approved Change Requests Described in Section 4.4.1.4. 5.3.2 Create WBS: Tools and Techniques .1 Work Breakdown Structure Templates Although each project is unique, a WBS from a previous project can often be used as a template for a new project, since some projects will resemble another prior project to some extent. For example, most projects within a given organization will have the same or similar project life cycles and, therefore, have the same or similar deliverables required from each phase. Many application areas or performing organizations have standard WBS templates. The Project Management Institute Practice Standard for Work Breakdown Structures provides guidance for the generation, development, and application of work breakdown structures. This publication contains industry-specific examples of WBS templates that can be tailored to specific projects in a particular application area. A portion of a WBS example, with some branches of the WBS decomposed down through the work package level, is shown in Figure 5-6. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 113 NAVIGATION LINKS ABBREVIATION LIST Chapter 5 − Project Scope Management Figure 5-6. Sample Work Breakdown Structure with Some Branches Decomposed Down Through Work Packages .2 Decomposition Decomposition is the subdivision of project deliverables into smaller, more manageable components until the work and deliverables are defined to the work package level. The work package level is the lowest level in the WBS, and is the point at which the cost and schedule for the work can be reliably estimated. The level of detail for work packages will vary with the size and complexity of the project. Decomposition may not be possible for a deliverable or subproject that will be accomplished far into the future. The project management team usually waits until the deliverable or subproject is clarified so the details of the WBS can be developed. This technique is sometimes referred to as rolling wave planning. Different deliverables can have different levels of decomposition. To arrive at a manageable work effort (i.e., a work package), the work for some deliverables needs to be decomposed only to the next level, while others need more levels of decomposition. As the work is decomposed to lower levels of detail, the ability to plan, manage, and control the work is enhanced. However, excessive decomposition can lead to non-productive management effort, inefficient use of resources, and decreased efficiency in performing the work. The project team needs to seek a balance between too little and too much in the level of WBS planning detail. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 114 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS ABBREVIATION LIST Decomposition of the total project work generally involves the following activities: • Identifying the deliverables and related work • Structuring and organizing the WBS • Decomposing the upper WBS levels into lower level detailed components • Developing and assigning identification codes to the WBS components • Verifying that the degree of decomposition of the work is necessary and sufficient. 5 Identifying the major deliverables of the project and the work needed to produce those deliverables requires analyzing the detailed project scope statement. This analysis requires a degree of expert judgment to identify all the work including project management deliverables and those deliverables required by contract. Structuring and organizing the deliverables and associated project work into a WBS that can meet the control and management requirements of the project management team is an analytical technique that may be done with the use of a WBS template. The resulting structure can take a number of forms, such as: • Using the major deliverables and subprojects as the first level of decomposition, as shown in Figure 5-6. • Using subprojects as illustrated in Figure 5-6, where the subprojects may be developed by organizations outside the project team. For example, in some application areas, the project WBS can be defined and developed in multiple parts, such as a project summary WBS with multiple subprojects within the WBS that can be contracted out. The seller then develops the supporting contract work breakdown structure as part of the contracted work. • Using the phases of the project life cycle as the first level of decomposition, with the project deliverables inserted at the second level, as shown in Figure 5-7. • Using different approaches within each branch of the WBS, as illustrated in Figure 5-8, where test and evaluation is a phase, the air vehicle is a product, and training is a supporting service. Decomposition of the upper level WBS components requires subdividing the work for each of the deliverables or subprojects into its fundamental components, where the WBS components represent verifiable products, services, or results. Each component should be clearly and completely defined and assigned to a specific performing organizational unit that accepts responsibility for the WBS component’s completion. The components are defined in terms of how the work of the project will actually be executed and controlled. For example, the status- reporting component of project management could include weekly status reports, while a product to be manufactured might include several individual physical components plus the final assembly. A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 115 NAVIGATION LINKS ABBREVIATION LIST Chapter 5 − Project Scope Management Verifying the correctness of the decomposition requires determining that the lower-level WBS components are those that are necessary and sufficient for completion of the corresponding higher-level deliverables. Figure 5-7. Sample Work Breakdown Structure Organized by Phase Figure 5-8. Sample Work Breakdown for Defense Materiel Items A Guide to the Project Management Body of Knowledge (PMBOK ® Guide) Third Edition 116 2004 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS ABBREVIATION LIST [...]... Third Edition 20 04 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA 6 Figure 6-1 Project Time Management Overview ® A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS 125 ABBREVIATION LIST Chapter 6 − Project Time Management Note:... performing the six processes of Project Time Management is preceded by a planning effort by the project management team This planning effort is part of the Develop Project Management Plan process (Section 4. 3), which produces a schedule management plan that sets the format and establishes criteria for developing and controlling the project schedule The project time management processes, and their associated... Replanning Approved change requests affecting the project scope can require modifications to the WBS and WBS dictionary, the project scope statement, and the project scope management plan These approved change requests can cause updates to components of the project management plan .4 5 Configuration Management System A formal configuration management system (Section 4. 3.2.2) provides procedures for the status... to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS 121 ABBREVIATION LIST Chapter 5 − Project Scope Management 4 5 Requested Changes The results of project scope control can generate requested changes, which are processed for review and disposition according to the project. .. 5.3.3.3 .4 Project Scope Management Plan Described in Section 5.1.3.1 .5 Performance Reports Performance reports provide information on project work performance, such as interim deliverables that have been completed .6 Approved Change Requests An approved change request (Section 4. 4.1 .4) impacting project scope is any modification to the agreed-upon project scope baseline, as defined by the approved project. .. part of the project life cycle (Section 2.1), and are documented in the schedule management plan The schedule management plan is contained in, or is a subsidiary plan of, the project management plan (introduction to Section 4. 3), and may be formal or informal, highly detailed or broadly framed, based upon the needs of the project 1 24 NAVIGATION LINKS ABBREVIATION LIST ® A Guide to the Project Management. .. WBS dictionary .7 120 Project Scope Statement The project scope statement, along with its associated WBS and WBS dictionary (Section 5.3), defines the project s scope baseline and product scope Work Performance Information Described in Section 4. 4.3.7 NAVIGATION LINKS ABBREVIATION LIST ® A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute,... computer program code, or chapters in a book The activity list is used in the schedule model and is a component of the project management plan (Section 4. 3) The schedule activities are discrete components of the project schedule, but are not components of the WBS ® A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute, Four Campus Boulevard,... dictionary .4 5 Scope Baseline The approved detailed project scope statement (Section 5.2.3.1) and its associated WBS and WBS dictionary are the scope baseline for the project ® A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA NAVIGATION LINKS 117 ABBREVIATION LIST Chapter 5 − Project. .. being produced and accepted are included in the approved project scope NAVIGATION LINKS ABBREVIATION LIST ® A Guide to the Project Management Body of Knowledge (PMBOK Guide) Third Edition 20 04 Project Management Institute, Four Campus Boulevard, Newtown Square, PA 19073-3299 USA .3 Project Scope Management Plan Described in Section 5.1.3.1 .4 Deliverables The deliverables are those that have been . Section 4. 1.1 .4. .2 Project Scope Statement Described in Section 5.2.3.1. .3 Project Scope Management Plan Described in Section 5.2.1 .4. .4 Approved Change Requests Described in Section 4. 4.1 .4. . projects that may be located in the lessons learned knowledge base. .3 Project Charter Described in Section 4. 1. .4 Preliminary Project Scope Statement Described in Section 4. 2. .5 Project. .1 Project Scope Management Plan The project scope management plan provides guidance on how project scope will be defined, documented, verified, managed, and controlled by the project management

Ngày đăng: 10/08/2014, 07:21

Từ khóa liên quan

Mục lục

  • Project Management Body of Knowledge

    • Section III The Project Management Knowledge Areas

      • Chapter 5 - Project Scope Management

        • 5.1 Scope Planning

          • 5.1.1 Scope Planning: Inputs

          • 5.1.2 Scope Planning: Tools and Techniques

          • 5.1.3 Scope Planning: Outputs

          • 5.2 Scope Definition

            • 5.2.1 Scope Definition: Inputs

            • 5.2.2 Scope Definition: Tools and Techniques

            • 5.2.3 Scope Definition: Outputs

            • 5.3 Create WBS

              • 5.3.1 Create WBS: Inputs

              • 5.3.2 Create WBS: Tools and Techniques

              • 5.3.3 Create WBS: Outputs

              • 5.4 Scope Verification

                • 5.4.1 Scope Verification: Inputs

                • 5.4.2 Scope Verification: Tools and Techniques

                • 5.4.3 Scope Verification: Outputs

                • 5.5 Scope Control

                  • 5.5.1 Scope Control: Inputs

                  • 5.5.2 Scope Control: Tools and Techniques

                  • 5.5.3 Scope Control: Outputs

                  • Chapter 6 - Project Time Management

                    • 6.1 Activity Definition

                      • 6.1.1 Activity Definition: Inputs

                      • 6.1.2 Activity Definition: Tools and Techniques

                      • 6.1.3 Activity Definition: Outputs

                      • 6.2 Activity Sequencing

                        • 6.2.1 Activity Sequencing: Inputs

                        • 6.2.2 Activity Sequencing: Tools and Techniques

Tài liệu cùng người dùng

  • Đang cập nhật ...

Tài liệu liên quan